  2022 Road Maintenance Bid Specs                  
                     
Location Priority Code From To Length (WISLR) Width Shoulders Cut & Fill Treatment Thickness Notes
Coon Bluff Rd 2 Oak Leaf Lane CTH H 3379 20 12′   Seal N/A Completion by 6/30/22
Dellwood Rd 2 2000′ US 23 2000′ 18 12   Mill & Pave 2.5″ Completion by 6/30/22
Lyndon Road 2 CTH P Berry Rd 3960 20 12 GSF Mill & Pave 2.5 Completion by 6/30/22
Turtle Rd 2 As Needed   TBD 18 12 GSF Shldr Repair N/A TBD
Lark Rd 3 All   2000 18 12″   Wdg/Seal N/A Completion by 8/1/2022
N Ladyslipper Ct 4 TBD   958 18 12″   Wdg/Seal N/A Completion by 8/1/2022
Wildflower Dr 4 All   3960 18 12″   Wdg/Overlay 2″ Completion by 6/30/22
Xmas Mtn Dr 4 All   1848 18 12″   Seal N/A Completion by 6/30/22
Xmas Mtn Rd 4 All   6917 18 12″   Seal N/A Completion by 6/30/22
                     
Conditions:                    
  1.  Single pass paved surface                
  2.  Thickness is minimum across entire surface of paving            
  3.  Completion date as specified              
  4.  Load slips required for each project              